TSMC Eyes $22.6 Billion Chip Plant Near College Station
By Uriel Garcia
November 24, 2026
BRAZOS COUNTY, Texas — TSMC has filed an application with the Texas Comptroller under the state's Jobs, Energy, Technology and Innovation (JETI) program as it evaluates a Brazos County site for the proposed TSMC Texas Advanced Semiconductor Manufacturing Campus, Brazos County announced on November 23.
A Leading-Edge Fab for Texas
The application says the campus would include one or more semiconductor fabrication facilities. The plant would make leading-edge logic chips using 2-nanometer or more advanced process technology for artificial intelligence, high-performance computing and mobile uses. The county noted that it is a semiconductor manufacturing facility, not a data center.
• Investment: $22.6 billion
• Jobs: at least 2,099 direct jobs
• Average annual salary: $133,000
Site and Timeline
The proposed 3,231.8-acre site is in Brazos County Precinct 1, near Koppe Bridge Road and I & GN Road, within the City of College Station's extraterritorial jurisdiction and College Station ISD. The state posted the application, J0055, filed by TSMC Arizona Corporation, on November 23.
Projected timeline:
• Construction: 2027 through 2031
• Commercial operations: 2031
• Hiring: 757 jobs in 2028, 1,110 in 2029 and 232 in 2030 according to TSMC’s projections.
Next Steps
The project still needs required approvals and TSMC's final investment decision. The application says TSMC is comparing the Brazos County site with options outside Texas, particularly Arizona. It also says agreements signed so far to explore land purchases are nonbinding and do not commit the company to buy the land or choose the site.
The JETI process includes review by the Comptroller and approval by the Governor and the College Station ISD Board of Trustees.
"We are very excited about this potential transformational opportunity for our citizens," said Brazos County Manager Trevor Lansdown.
The county is working with College Station, Bryan, College Station ISD, Texas A&M University and the Greater Brazos Partnership, and plans a public town hall soon.
What It Could Mean for Texas Manufacturing
The proposal is not final. Still, a $22.6 billion fab with at least 2,099 direct jobs would place advanced chipmaking in the heart of the state and widen the supplier and workforce base that manufacturers across Texas, including South Texas, depend on.