Blue Energy's Port of Victoria Nuclear Plant Clears Key NRC Review Milestone
By Uriel Garcia
November 17, 2026
VICTORIA, Texas — Blue Energy announced on November 16, 2026, that the U.S. Nuclear Regulatory Commission (NRC) has accepted the first part of its construction permit application for Blue Energy Center – Port of Victoria, a first-of-its-kind gas-to-nuclear power plant planned in Victoria County. The acceptance means the NRC has found the application ready for detailed safety and environmental review.
Keeping the Project on Schedule
Blue Energy submitted Part 1 of the application in September and expects to file Part 2 in the second half of 2027. The NRC also accepted the company's "Blue Hybrid" approach, which the company says can cut costs and time to power.
“Acceptance of this application keeps Blue Energy’s Texas power plant on its accelerated timeline to provide the state and customers with reliable, grid-connected nuclear power,” said CJ Fong, Vice President of Regulatory Affairs at Blue Energy.
Gas First, Then Small Modular Reactors
The plant will first bring GE Vernova 7HA.02 gas turbines online, along with infrastructure later used by GE Vernova Hitachi BWRX-300 small modular reactors. Major plant supermodules will be prefabricated offsite and delivered by barge, and the privately financed project remains subject to a final investment decision in 2027.
A Major Investment for the Crossroads
According to the City of Victoria, the project is estimated at full build-out to create $6.2 billion in taxable assets and 363 permanent jobs with an average annual salary of $140,000, along with training opportunities with local higher education.
By pairing new base load power with port infrastructure at the Texas Logistics Center, Blue Energy's plant positions Victoria and the Coastal Bend to attract energy-intensive manufacturing, strengthen grid reliability for South Texas industry and create high-wage careers for the region's workforce.